Mahar Aung Myay Residence

This 2.5 stories residential construction was located in Mandalay and completed successfully within 7 month. The modern style 2.5 stories was built in 2018, the construction started in January 2018 and finished in July 2018. The whole construction project costs 65 million kyats. This building has floor area of 20’x60’on each floor and reinforced cement concrete structure.

Construction Detail

Project Name 2.5 Stories RCC Residential Building
Address Mahar Aung Myay Township, Mandalay
Starting Date 31.1.2018
Completion Date  14.7.2018
Employer Name U Pike and Daw Toe
Contract Value 65 Million Kyats
Construction Type 2.5 Stories RCC Building
Construction Detail 2.5 (20'x60'), RCC Building